SAP C-TS422-1909 Exam Description:

The "SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing" certification exam validates that the candidate possesses the fundamental and core knowledge required of the SAP S/4HANA Manufacturing consultant profile. This certification proves that the candidate has an overall understanding and in‐depth technical skills to participate as a member of a project team in a mentored role.

 

NEW QUESTION 21
A warehouse manager likes to streamline the goods receipt (GR) process for production orders. Where can you enable the automatic GR?
There are 2 correct answers to this question.
Response:

  • A. Production scheduling profile
  • B. Operation control key
  • C. Confirmation profile
  • D. Scheduling margin key

Answer: A,B

 

NEW QUESTION 22
The material master of your finished product contains MRP type "PD". You set a manual firming date in the stock requirements list. Which of the following will firm planned orders" There are 2 correct answers to this question.
Response:

  • A. Assigning a production scheduling profile
  • B. Creating a planned order within the planning time fence
  • C. Setting a planning time fence in the Material Master Record
  • D. Manually changing the quantity of a planned order

Answer: B,C

 

NEW QUESTION 23
Which document is skipped when SAP EWM is embedded in SAP S/4HANA?
Please choose the correct answer.
Response:

  • A. Warehouse order
  • B. Outbound delivery order
  • C. Outbound delivery request
  • D. Warehouse task

Answer: C

 

NEW QUESTION 24
What does a line hierarchy in repetitive manufacturing represent?

  • A. A production line with prioritized alternative work centers
  • B. A production line with more than one work center
  • C. A production line with a parallel sequence in the routing
  • D. A production line with an alternative sequence in the routing

Answer: B

 

NEW QUESTION 25
You want to reduce planning efforts for B/C materials. Which planning procedure do you recommend?

  • A. Consumption-based planning
  • B. Manual planning without check
  • C. Material requirements planning
  • D. Forecast planning

Answer: A

 

NEW QUESTION 26
What do you use to schedule operations from planned orders so that the production plan can be fulfilled?

  • A. Material Requirements Planning (MRP)
  • B. Capacity Requirements Planning (CRP)
  • C. Demand Planning (DP)
  • D. Supply Network Planning (SNP)

Answer: A

 

NEW QUESTION 27
On which of the following levels can you influence the availability check for the components of production orders?
There are 2 correct answers to this question.
Response:

  • A. Material master
  • B. Production controller
  • C. MRP controller
  • D. Production order type

Answer: A,C

 

NEW QUESTION 28
How can you carry out cost object controlling for production orders? Note: There are 2 correct answers to this question.

  • A. Cost-related
  • B. Order-related
  • C. Milestone-related
  • D. Product-related

Answer: B,D

 

NEW QUESTION 29
What are drawbacks of the separation of OLTP and OLAP?
There are 4 correct answers to this question.
Response:

  • A. The OLAP system needs to write back the data to the OLTP system
  • B. Only the OLAP system has a predefined subset of the data
  • C. Batch process are required to keep OLTP and OLAP in sync
  • D. Multiple copies of the data exist
  • E. Only the OLAP system has the latest data

Answer: A,B,C,D

 

NEW QUESTION 30
In order to use strategy 70 - Planning At Assembly Level, what order field must be set besides the planning strategy?
Please choose the correct answer.
Response:

  • A. Individual/Collective Indicator
  • B. Mixed MRP indicator
  • C. Dependent Requirements indicator
  • D. Storage Location MRP Indicator

Answer: B

 

NEW QUESTION 31
Which warehouse management functions are available in SAP EWM but NOT in SAP WM?
There are 3 correct answers to this question.
Response:

  • A. Expected goods receipt
  • B. Yard Management
  • C. Handling Unit Management
  • D. Labor Management
  • E. Slotting

Answer: A,D,E

 

NEW QUESTION 32
The production plan is being disrupted by last minute demands that are entered in the system. Which is the most efficient way to handle last minute demands and protect the current production plan?
There are 2 correct answers to this question.
Response:

  • A. In the material master record, set MRP type to P1 and a planning time fence on the replenishment lead time of the material
  • B. Manually firm all planned orders for materials within the replenishment lead time of the material
  • C. In the stock requirements list, set a manual firming fence for a date based on the replenishment lead time of the material
  • D. In the material master record, set MRP type to P4 and a planning time fence on the replenishment lead time of the material

Answer: A,C

 

NEW QUESTION 33
What are pillars of SAP Activate?
There are 2 correct answers to this question.
Response:

  • A. Guided Configuration
  • B. SAP Best Practices
  • C. Premium engagement
  • D. SAP MaxAttention

Answer: A,B

 

NEW QUESTION 34
Where does the system check master data selection settings during the creation of planned orders and production orders? Note: There are 3 correct answers to this question.

  • A. In the MRP controller
  • B. In the production order type
  • C. In the production version
  • D. In the routing
  • E. In the bill of materials (BOM)

Answer: A,B,D

 

NEW QUESTION 35
Which of the following business processes are controlled by parameters that are dependent on production order type? Note: There are 2 correct answers to this question.

  • A. Engineering change management
  • B. Planning
  • C. Inspection during production
  • D. Implementation

Answer: B,D

 

NEW QUESTION 36
What are the possible results of a production planning run in Advanced Planning (PP/OS)? Note: There are 3 correct answers to this question.

  • A. Scheduling agreement schedule line
  • B. Planned order
  • C. Stock transport order
  • D. Purchase requisition
  • E. Production order

Answer: A,B,D

 

NEW QUESTION 37
Which material-specific information can be transferred to a transportation lane in PP/DS?
There are 3 correct answers to this question.
Response:

  • A. Purchasing info records
  • B. Outline agreement
  • C. Quota arrangements
  • D. Production versions
  • E. Special procurement keys

Answer: A,B,E

 

NEW QUESTION 38
What are properties of MRP Live?
There are 2 correct answers to this question.
Response:

  • A. The code is written in SQL Script
  • B. Data is read sequentially from the database tables
  • C. It uses the same BAdis as classic MRP
  • D. It is executed on the database server

Answer: A,D

 

NEW QUESTION 39
......


SAP C-TS422-1909 Exam Syllabus Topics:

TopicDetails
Topic 1
  • Outline both motivation and background of SAP S/4HANA
  • Determine BOM item category
  • Describe order status management and set user statuses
Topic 2
  • Select and apply planning strategies, use the planning table
  • Advanced Planning in SAP S/4HANA
Topic 3
  • Differentiate consumption-based planning vs. MRP, outline new trends in production planning
  • Configure availability check for components
Topic 4
  • Introduction to SAP S/4HANA Production Planning
  • Outline production planning components and functions
Topic 5
  • Introduction to SAP S/4HANA Supply Chain Planning
  • Material Requirements Planning in SAP S/4HANA
Topic 6
  • Describe the SAP HANA database concept and new user experience with SAP Fiori
  • Identify and explain production relevant master data
Topic 7
  • Outline best practices for using SAP S/4HANA
  • Production Orders in SAP S/4HANA
Topic 8
  • Explain line load planning and confirmation
  • outline the capabilities of embedded analytics
Topic 9
  • Explain and compare the different production methods in make-to-order
  • Outline the basics and master data of advanced planning
Topic 10
  • Identify repetitive manufacturing specific master data
  • Apply material staging and confirmation

 