View All ISO-9001-Lead-Auditor Actual Exam Questions Answers and Explanations for Free May-2026 [Q90-Q113]

Share

View All ISO-9001-Lead-Auditor Actual Exam Questions Answers and Explanations for Free May-2026

The Most In-Demand PECB ISO-9001-Lead-Auditor Pass Guaranteed Quiz 

NEW QUESTION # 90
The following are stages of an audit, put them in the order they would be conducted.

Answer:

Explanation:

Explanation:
Establishing the audit programme objectives
Determining and evaluating the audit programme risks and opportunities
Establishing the audit programme
Initiating the audit
Preparing all audit activity
Conducting the audit activities
According to ISO 19011:2018, clause 5, the audit programme is a set of one or more audits planned for a specific time frame and directed towards a specific purpose. The audit programme includes all activities necessary to plan, organize, and conduct the audits. The audit programme management involves the following steps1:
Establishing the audit programme objectives: The audit programme objectives define the intended outcomes of the audit programme, such as verifying conformity, evaluating performance, identifying improvement opportunities, etc. The audit programme objectives should be aligned with the strategic direction and policies of the organization and the needs and expectations of the interested parties.
Determining and evaluating the audit programme risks and opportunities: The audit programme risks and opportunities are the factors that can affect the achievement of the audit programme objectives, such as changes in the internal or external context, availability of resources, competence of auditors, etc. The audit programme risks and opportunities should be identified, analyzed, and evaluated to determine the appropriate actions to address them.
Establishing the audit programme: The audit programme is established by defining the audit programme scope, criteria, methods, and resources. The audit programme scope defines the extent and boundaries of the audit programme, such as the processes, functions, sites, activities, etc. that will be audited. The audit programme criteria are the set of policies, procedures, or requirements used as a reference for the audits. The audit programme methods are the techniques used to conduct the audits, such as interviews, observations, document review, sampling, etc. The audit programme resources are the human, technical, and financial resources needed to implement the audit programme.
Initiating the audit: The audit initiation is the process of formally establishing the arrangements for an individual audit within the audit programme. The audit initiation involves contacting the auditee and the audit client, confirming the audit objectives, scope, and criteria, and obtaining the necessary information and access for the audit.
Preparing all audit activity: The audit preparation is the process of developing the audit plan and the audit work documents for an individual audit. The audit plan is a document that provides the basis for agreement regarding the conduct of the audit, such as the audit schedule, the audit team, the audit methods, the audit language, the audit report, etc. The audit work documents are the records that provide evidence of the audit activities, such as the audit checklist, the audit notes, the audit findings, etc.
Conducting the audit activities: The audit activities are the processes of collecting and verifying audit evidence and evaluating it against the audit criteria to make the audit conclusions. The audit activities include the opening meeting, the communication during the audit, the roles and responsibilities of the audit team and the auditee, the audit evidence collection and verification, the audit findings generation and recording, the closing meeting, and the audit report preparation and distribution.
References: ISO 19011:2018(en), Guidelines for auditing management systems


NEW QUESTION # 91
Select the words that best complete the sentence:

Answer:

Explanation:

Explanation:
According to the ISO 19011:2018 document, the audit plan should provide the basis for agreement regarding the conduct and scheduling of the audit activities. The amount of detail provided in the audit plan should reflect the scope and complexity of the audit, as well as the risk of not achieving the audit objectives1. The scope of the audit refers to the extent and boundaries of the audit, such as the audit criteria, the audit objectives, the organizational and functional units, and the processes to be audited1. The complexity of the audit refers to the degree of difficulty or intricacy of the audit, such as the number and diversity of the auditees, the audit criteria, the audit methods, and the audit team composition2. The risk of not achieving the audit objectives refers to the possibility that the audit may fail to provide reliable and sufficient audit evidence to support the audit conclusions and report1.
Therefore, the complete sentence is:
In the context of a third-party audit, the amount of detail provided in the audit plan should reflect the scope and complexity of the audit, as well as the risk of not achieving the audit objectives.
References: 1: ISO 19011:2018 - Guidelines for auditing management systems 2: Audit Complexity - an overview | ScienceDirect Topics


NEW QUESTION # 92
Match the following potential audit client options to the type of audit.

Answer:

Explanation:

Explanation:
First-party Management System audit # All members of an audited organisation Second-party Management System audit # Interested parties of an organisation According to ISO 19011:2018 (Guidelines for Auditing Management Systems) and as reinforced in ISO
9001 Lead Auditor training materials, audit types are defined as:
* First-party audit - conducted by the organization itself, or on its behalf (internal audit).# The audit client is all members of the audited organisation, because the audit is internal, involving all functional areas under the organization's control.
* Second-party audit - conducted by a customer or other person on behalf of a customer (external but not by a certification body).# The audit client includes interested parties of an organisation, such as customers who want to verify if their suppliers meet contractual or regulatory requirements.
These definitions are directly aligned with ISO 19011:2018, Clause 3.13 - Types of audits.
Why Other Options Are Incorrect:
* Certification body / Accreditation body # These relate to third-party audits, not first or second.
* Top management / Functions of an audited organisation # Refer to auditees or audit participants, not the audit client itself.
References:
ISO 19011:2018 Clause 3.13 - Types of audits
ISO 9001:2015 Clause 9.2 - Internal audit
ISO Definitions for First-party, Second-party, and Third-party audits


NEW QUESTION # 93
An organisation decides to purchase products and services only from ISO 9001 certified suppliers.
Match the four organisational functions to a potential benefit.

Answer:

Explanation:

Explanation:
Reduced incoming inspection # A. Quality
Improved communication with suppliers # B. Procurement
Purchased materials received on time # C. Logistics
Reduced variability within processes # D. Production
According to ISO 9001:2015, Clause 8.4 - Control of externally provided processes, products and services, organisations are required to ensure that externally provided products and services conform to specified requirements. When an organisation sources from ISO 9001 certified suppliers, there is greater assurance of consistency in quality, delivery, and communication. This enhances internal operations across various functions:
Reduced incoming inspection (Quality): ISO 9001 certified suppliers have robust quality controls (Clause
8.4.2), reducing the need for repeated inspections upon receipt. This aligns with Quality's responsibility for incoming inspection and verification.
Improved communication with suppliers (Procurement): Clause 8.4.3 emphasizes the communication of detailed requirements to external providers. Procurement plays a key role in ensuring these requirements are understood and met.
Purchased materials received on time (Logistics): Timely deliveries are often a result of structured supplier evaluation and selection (Clause 8.4.1). Logistics benefits through fewer delays and better scheduling of internal processes.
Reduced variability within processes (Production): Consistency of supplied materials supports stable and predictable production processes, which is a key aspect of Clause 8.5 - Production and service provision.
References:
ISO 9001:2015 Clause 8.4.1 - General
ISO 9001:2015 Clause 8.4.2 - Type and extent of control
ISO 9001:2015 Clause 8.4.3 - Information for external providers
ISO 9001:2015 Clause 8.5 - Production and service provision


NEW QUESTION # 94
Select the word that best completes the sentence:

Answer:

Explanation:

Explanation:

According to the ISO - Management system standards page, the key benefits of an effective management system include improved operational effectiveness and efficiency, improved risk management and protection of people and the environment, and enhanced drive for innovation. The Integrated Use of Management System Standards (IUMSS) handbook also states that the purpose and objectives of management system standards are to help organizations improve their performance by specifying repeatable steps that organizations consciously implement to achieve their goals and objectives.
Therefore, the complete sentence is:
"The purpose of a management system standard is to improve the performance of an organisation."


NEW QUESTION # 95
You are carrying out an audit at an organisation seeking certification to ISO 9001 for the first time. The organisation offers regulatory consultancy services to manufacturers of cosmetics. The business operates from ten regional offices.
You are nearing the end of the audit and need to decide if sufficient evidence of top management leadership and commitment with respect to the quality management system has been gathered.
Which four of the following would demonstrate top management leadership and commitment with respect to the quality management system?

  • A. Promoting the importance of following procedures
  • B. Briefing staff on the development of an improvement culture
  • C. Chairing management review meetings
  • D. Not attending audit closing meeting
  • E. Conducting staff disciplinary meetings
  • F. Investing time and money in corrective actions arising from nonconformities
  • G. Approving company car budgets for the fiscal year

Answer: A,B,C,F

Explanation:
To demonstrate top management's leadership and commitment with respect to the quality management system, the following four actions would be indicative:
B: Briefing staff on the development of an improvement culture: This shows that top management is actively involved in promoting a culture of continuous improvement, which is a key aspect of the quality management system1.
C: Chairing management review meetings: By leading these meetings, top management demonstrates their involvement in the quality management system's ongoing performance and commitment to its continual improvement1.
E: Investing time and money in corrective actions arising from nonconformities: This indicates that top management is committed to addressing issues and ensuring that the quality management system is effective and continually improving1.
G: Promoting the importance of following procedures: When top management emphasizes the importance of adherence to procedures, it reinforces the significance of the quality management system and its processes1.
These actions align with the requirements of ISO 9001:2015, which emphasizes the need for top management to take accountability for the effectiveness of the quality management system and to promote a focus on continual improvement and customer satisfaction123. Approving company car budgets, conducting disciplinary meetings, and not attending the audit closing meeting do not directly demonstrate leadership and commitment to the quality management system1.


NEW QUESTION # 96
You are carrying out an audit to ISO 9001 at an organisation which offers consultancy services on the implementation of ISO 9001 quality management systems to manufacturers of cosmetics.
You are interviewing the Technical and Quality Director (TQD), who manages a team of biochemists responsible for providing ISO 9001 consultancy services to customers.
You: "How do you ensure your team's competence concerning regulatory and ISO 9001 requirements?" TQD: "We subcontract a part-time lead consultant who has years of experience working as a biochemist in the cosmetics industry. She is responsible for ensuring the team's competency." You: "Do they retain any documented information on the individual competency of each consultant?" TQD: "No. The lead consultant is a dedicated individual with lots of contacts in the sector. We rely on her decision on the consultants' competency. She says that she thought that it was not necessary to keep documented information; however, after the event two weeks ago, which could not be solved due to the lack of documentation, she may consider in the future to plan which information we may need to keep." You: "How does the organisation enable the consultants you employ to maintain updated their competence on ISO 9001 and regulatory requirements?" TQD: "As I said before, we leave that up to the lead consultant. She tells us when we need to employ more young consultants and when changes are introduced in the applicable regulations. Our regular survey shows that customers are quite satisfied with our consultants; last year's objective of customer satisfaction was achieved. We gave a salary increase to consultants when they knew that the objectives had been achieved." You decide to raise a non-conformity.
To complete the non-conformity report, click on the blank section you want to complete so it is highlighted in red and then click on the applicable text from the options below. Alternatively, drag and drop the options to the appropriate blank section.

Answer:

Explanation:

Explanation:
Non-conformity Report
ISO 9001 Clause Number:
7.2
Nature of problem:
Documented information is not retained on the necessary competence of consultants with respect to relevant regulatory and ISO 9001 requirements.
ISO 9001 requirement that has not been fulfilled:
ISO 9001 - "The organization shall retain appropriate documented information as evidence of competence." ISO 9001:2015 places a clear requirement on organisations to ensure that persons doing work under its control that affects performance and conformity are competent, and that this competence is demonstrated and evidenced.
Relevant ISO 9001 requirements
* Clause 7.2 - Competence requires the organisation to:
* determine the necessary competence of persons doing work under its control,
* ensure that these persons are competent on the basis of appropriate education, training, or experience, and
* retain appropriate documented information as evidence of competence.
In the scenario:
* Competence decisions are entirely delegated to a subcontracted lead consultant.
* No documented information is retained to demonstrate individual consultant competence.
* A recent event could not be resolved specifically due to the absence of documented competence records, which directly confirms non-fulfilment of Clause 7.2.
* Reliance on customer satisfaction results or the personal judgement of a consultant does not replace the ISO 9001 requirement for objective evidence.
Why other clauses are not applicable:
* Clause 7.1 relates to provision of resources, not evidence of competence.
* Clause 7.3 relates to awareness of quality objectives, not competence records.
* Statements such as "consultants are not aware of customer satisfaction objectives" or "persons necessary are not determined" are not supported by the scenario evidence.
ISO-aligned conclusion:
The organisation has failed to retain documented information as evidence of competence for consultants providing ISO 9001 and regulatory consultancy services. This is a clear and justified nonconformity against ISO 9001:2015 Clause 7.2.


NEW QUESTION # 97
During a third-party audit of a pharmaceutical organisation (CD9000) site of seven COVID-19 testing laboratories in various terminals at a major international airport, you interview the CD 9000's General Manager (GM), who was accompanied by Jack, the legal compliance expert. Jack is acting as the guide in the absence of the Technical Manager due to him contracting COVID-19.
You: "What external and internal issues have been identified that could affect CD9000 and its quality management system?" GM: "Jack guided us on this. We identified issues like probable competition of another laboratory organisation in the airport, legal requirements on COVID-19 continuously changing, the shortage of competent laboratory analysists, the epidemic declining soon, shortage of chemicals for the analysis. It was quite a good experience." You: "Did you document these issues?" GM: "No. Jack said that ISO 9001 does not require us to document these issues." You: "How did you determine the risks associated with the issues and did you plan actions to address them?" GM: "I am not sure. The Technical Manager is responsible for this process. Jack may be able to answer this question in his absence." Select two options for how you would respond to the General Manager's suggestion:

  • A. I would ask to audit the Technical Manager by phone.
  • B. I would delay the audit until the return of the technical manager
  • C. I would not accept the legal compliance expert answering the question.
  • D. I would ask for a different guide instead of the legal compliance expert.
  • E. I would look for evidence that the actions resulting from the risk assessment had been taken.
  • F. I would ask the consultant to leave the meeting since he is not an employee of the organisation.

Answer: C,E

Explanation:
According to clause 4.1 of ISO 9001:2015, the organization should determine external and internal issues that are relevant to its purpose and its strategic direction and that affect its ability to achieve the intended results of its quality management system. The organization should monitor and review these issues and update them as necessary. Although the standard does not explicitly require documented information of these issues, it does require documented information as evidence of the implementation of the actions taken to address risks and opportunities, as per clause 6.1. The organization should also retain documented information as evidence of the results of the monitoring, measurement, analysis and evaluation of its QMS, as per clause 9.1. Therefore, the auditor should not accept the legal compliance expert answering the question, as he is not the person responsible for the process and may not have the necessary competence or knowledge of the QMS. The auditor should also look for evidence that the actions resulting from the risk assessment had been taken, as this is a requirement of the standard and a way to verify the effectiveness of the QMS. The other options are not appropriate courses of action for the auditor, because they do not address the audit objective or criteria, or they may compromise the audit integrity or impartiality. For example, option B may not be feasible or reliable, as the Technical Manager may not be available or able to provide the necessary evidence by phone. Option C may cause unnecessary delay and inconvenience for the audit process and the auditee. Option E may not solve the problem, as the guide is not the main source of evidence or information for the audit. Option F may be disrespectful or unprofessional, as the consultant may have a legitimate role or interest in the audit.
References: ISO 9001:2015, ISO 9001 Auditing Practices Group Guidance on Context of the Organization, ISO 9001 Auditing Practices Group Guidance on Audit Evidence


NEW QUESTION # 98
The certification body has not been able to verify the implementation of corrective actions for any identified major nonconformity within six months after the last day of the Stage 2 audit. What must the certification body do in this case?

  • A. It must issue an unfavorable recommendation of certification
  • B. It must conduct all audit activities from the beginning
  • C. It must conduct another Stage 2 audit before granting certification

Answer: A

Explanation:
Comprehensive and Detailed In-Depth Explanation:According to ISO 17021-1:2015, Clause 9.4.10 (Corrective Actions for Major Nonconformities):
* If a major nonconformity is not corrected within six months, the certification body must reject the certification request.
* Another Stage 2 audit (C) is not required unless the organization reapplies for certification.
* Restarting all audit activities (B) is unnecessary; instead, certification is denied.
Thus, A is the correct answer.


NEW QUESTION # 99
What does the application of the process approach in a QMS enable?

  • A. The reduction of resource consumption
  • B. The improvement of processes based on the needs and expectations of interested parties
  • C. The achievement of effective process performance
  • D. The consideration of processes in terms of financial value

Answer: C

Explanation:
Comprehensive and Detailed In-Depth Explanation:ISO 9001:2015 promotes the process approach, which allows organizations to structure their activities into interrelated processes. This approach helps ensure that processes effectively achieve intended results.
Clause 0.3.1 (Process Approach) states that "The application of the process approach in a quality management system enables understanding and consistency in meeting requirements, considering processes in terms of added value, and achieving effective process performance." This aligns directly with option C, making it the correct answer. The other options are either partially correct or do not fully capture the purpose of the process approach:
* Option A (Improvement based on interested parties) is a benefit but does not define the main goal.
* Option B (Financial value) is not the primary focus of the process approach.
* Option D (Reduction of resource consumption) may be an indirect benefit but is not a core objective.


NEW QUESTION # 100
Put the following steps of a third-party audit into the correct sequence in which they happen.

Answer:

Explanation:

Explanation:
Sequence:
Stage 1 Audit
Stage 2 Opening Meeting
Interviews
Stage 2 Closing Meeting
Close-out of Stage 2 Audit Findings
Issue Certificate
Surveillance Audit
Follow-up Audit
To complete the sequence, you can drag and drop the options to the appropriate blank section.
Here is a brief explanation of each step:
Stage 1 Audit: This is the initial audit that aims to assess the readiness of the organization for the stage 2 audit. It involves reviewing the documentation of the quality management system, evaluating the scope and objectives of the audit, and identifying any major gaps or nonconformities34.
Stage 2 Opening Meeting: This is the meeting that marks the start of the stage 2 audit. It involves confirming the audit plan, the audit criteria, the audit scope, and the audit team. It also provides an opportunity for the auditee to ask any questions or raise any concerns34.
Interviews: This is the main activity of the stage 2 audit, where the audit team collects evidence by interviewing the personnel involved in the quality management system, observing the processes and activities, and examining the records and documents. The audit team uses various techniques, such as sampling, measurement, analysis, and evaluation, to verify the conformity and effectiveness of the quality management system345.
Stage 2 Closing Meeting: This is the meeting that marks the end of the stage 2 audit. It involves presenting the audit findings, the audit conclusions, and the audit report to the auditee. It also provides an opportunity for the auditee to provide feedback, ask questions, or dispute any findings34.
Close-out of Stage 2 Audit Findings: This is the process of verifying that the auditee has taken appropriate corrective actions to address any nonconformities or opportunities for improvement identified during the stage
2 audit. The audit team may request evidence or conduct a follow-up visit to confirm the effectiveness of the corrective actions34.
Issue Certificate: This is the process of issuing a certificate of conformity to the auditee, if the audit team is satisfied that the quality management system meets the requirements of the standard and that there are no major nonconformities or unresolved issues. The certificate is valid for a specified period, usually three years, and is subject to periodic surveillance audits34.
Surveillance Audit: This is the process of conducting periodic audits, usually once a year, to monitor the continued conformity and effectiveness of the quality management system. It involves reviewing the changes, improvements, and performance of the quality management system, and identifying any new nonconformities or opportunities for improvement34.
Follow-up Audit: This is the process of conducting an additional audit, usually in response to a significant change, a complaint, or a major nonconformity, to verify the impact and the corrective actions taken by the auditee. It may result in the suspension, withdrawal, or renewal of the certificate, depending on the outcome of the audit34.


NEW QUESTION # 101
Which of the options below is an example of minor nonconformity?

  • A. Some of the nonconformities were not closed as planned (on time) and no justification was provided or documented
  • B. Lack of corrective actions to address recurrent incidents
  • C. Lack of commitment from the top management

Answer: A

Explanation:
Comprehensive and Detailed In-Depth Explanation:
Minor nonconformities are isolated issues that do not significantly impact the QMS but still require correction.
* Failure to close nonconformities on time (Answer A) is a procedural issue and is considered minor unless it leads to repeated failures.
Major nonconformities include:
* Lack of top management commitment (Answer B), which affects leadership and strategic direction.
* Failure to take corrective actions for recurrent issues (Answer C), which indicates systemic failure.
Reference:
ISO 9001:2015, Clause 10.2 (Nonconformity and Corrective Action)


NEW QUESTION # 102
In the context of a third-party management system certification audit, which two of the following statements are correct?

  • A. The Stage 2 audit should include an opening meeting at the start of the audit and a closing meeting at the conclusion of the audit.
  • B. The purpose of a Stage 2 audit is to evaluate the implementation of the auditee's management system.
  • C. The Stage 2 audit must be conducted by auditors who have never worked for the auditee
  • D. A Stage 2 audit evaluates how efficiently the organisation is implementing its management system
  • E. The purpose of a Stage 2 audit is to certify an organisation to ISO 9001.
  • F. The Stage 2 audit cannot include remote access to electronic site(s) that contain information relevant to the audit of the management system.

Answer: A,B


NEW QUESTION # 103
Scenario 5: Mechanical-Electro (ME) Audit Stages
Mechanical-Electro, better known as ME, is an American company that provides mechanical and electrical services in China. Their services range from air-conditioning systems, ventilation systems, plumbing, to installation of electrical equipment in automobile plants, electronic manufacturing facilities, and food processing plants.
Due to the fierce competition from local Chinese companies and failing to meet customer requirements, ME's revenue dropped significantly. In addition, customers' trust and confidence in the company decreased, and the reputation of the company was damaged.
In light of these developments, the top management of ME decided to implement a quality management system (QMS) based on ISO 9001. After having an effective QMS in place for over a year, they applied for a certification audit.
A team of four auditors was appointed for the audit, including Li Na as the audit team leader. Initially, the audit team conducted a general review of ME's documents, including the quality policy, operational procedures, inventory lists, QMS scope, process documentation, training records, and previous audit reports.
Li Na stated that this would allow the team to maintain a systematic and structured approach to gathering documents for all audit stages. While reviewing the documented information, the team observed some minor issues but did not identify any major nonconformities. Therefore, Li Na claimed that it was not necessary to prepare a report or conduct a meeting with ME's representatives at that stage of the audit. She stated that all areas of concern would be discussed in the next phase of the audit.
Following the on-site activities and the opening meeting with ME's top management, the audit team structured an audit test plan to verify whether ME's QMS conformed to Clause 8.2.1 (Customer Communication) of ISO
9001.
To do so, they gathered information through group interviews and sampling. Li Na conducted interviews with departmental managers in the first group and then with top management. In addition, she chose a sampling method that sufficiently represented customer complaints from both areas of ME's operations.
The team members were responsible for the sampling procedure. They selected a sample size of 4 out of 45 customer complaints received weekly for electrical services and 2 out of 10 complaints for mechanical services.
Afterward, the audit team evaluated the evidence against the audit criteria and generated the audit findings.
According to general principles of sampling procedure, did the audit team select a valid sample for electrical services?

  • A. Yes, the selected sample size is proportionate to the population.
  • B. No, the selected sample size is high compared to the population, as for a population from 13 to 52 the minimum sample size should be 10.
  • C. No, the selected sample size is low compared to the population, as for a population from 13 to 52 the minimum sample size should be 5.

Answer: C

Explanation:
Comprehensive and Detailed In-Depth Explanation:
The audit team selected 4 out of 45 customer complaints for electrical services, which is too low based on standard statistical sampling methods. According to ISO 19011:2018 (Guidelines for Auditing Management Systems), for a population size between 13 and 52, a minimum sample size should be 5 to achieve a reasonable level of confidence.
This means the selected sample (4 complaints) was insufficient and did not align with standard sampling procedures. Therefore, the correct answer is A.
Reference:
ISO 19011:2018, Clause 6.4.5 (Sampling Methods in Auditing)


NEW QUESTION # 104
Which one of the following documents addresses audit time calculation for third-party certification audits?

  • A. ISO 19011
  • B. ISO 17021-1
  • C. ISO 9000
  • D. ISO 9001

Answer: B

Explanation:
ISO/IEC 17021-1 is the standard that specifies requirements for bodies providing audit and certification of management systems. It includes provisions for determining audit time for third-party certification audits, ensuring that the audits are conducted in a consistent, comparable, and reliable manner, which can be applied to a variety of management systems, including ISO 9001.
References: ISO/IEC 17021-1; IAF Mandatory Document for the Determination of Audit Time of Quality and Environmental Management Systems Certification


NEW QUESTION # 105
You, as auditor, are in dialogue with the quality lead and managing director of a small business that supplies specialist laboratory equipment and furniture.
You: "I'd like to look at how you manage change in the organisation. What changes have you made as a business, say, over the last 12 months?" Auditee: "We have made some strategic changes, the main one being that we no longer manufacture our own products in house." You: "That sounds like quite a significant change. What has been the impact of that?" Auditee: "We now mainly sell other manufacturers' products, under their brand names, and have outsourced manufacture of our own brand products to one of our suppliers. Unfortunately, we had to make six members of our staff redundant. This represents about 20% of our workforce, so this has been quite a challenging time." You: "I'm sure. What were the reasons for making the change?" Auditee: "Our manufacturing section was a small operation, and we struggled to cope with fluctuations in demand. During busy periods, we found it hard to meet lead times, and in quiet periods we had staff with little to do. This was having an impact on customer satisfaction and meant we had to charge premium prices that made our product uncompetitive." You: "How did you go about the change?" In relation to the auditor's question about how the change was managed, the auditee mentions the steps listed below. Match the ISO 9001 clauses to the steps.
To complete the table, click on the blank section you want to complete so it is highlighted in red and then click on the ISO 9001 clauses listed below. Alternatively, drag and drop each clause to show which step the requirement applies to.

Answer:

Explanation:

Explanation:

Here is the correct matching of ISO 9001:2015 clauses to the steps mentioned in the change management process:
* We identified risks and opportunities and fed these into our risk management processes.
* Clause 6.1 (Actions to address risks and opportunities)
* We found a suitable supplier.
* Clause 8.4 (Control of externally provided processes, products, and services)
* We monitored customer feedback and noticed an increase in negative feedback about lead times.
* Clause 9.1.2 (Customer satisfaction)
* We put together a plan for implementation.
* Clause 6.2.2 (Planning to achieve quality objectives)
* We monitored the performance of the new supplier.
* Clause 8.4.2 (Type and extent of control of external providers)
* We noticed that productivity targets were being missed.
* Clause 9.1.1 (Monitoring, measurement, analysis, and evaluation)
* We communicated the plan internally.
* Clause 7.4 (Communication)
* We looked at the data at the management review and decided we needed to do something different.
* Clause 9.3.2 (Management review inputs)
* We reorganised the staffing and implemented redundancies.
* Clause 7.1.2 (People)
* We set an objective to effectively implement the transition and outsource manufacturing.
* Clause 6.2.1 (Quality objectives and planning to achieve them)
This aligns the steps of the change process with relevant ISO 9001:2015 clauses related to risk, planning, communication, and monitoring.


NEW QUESTION # 106
Which of the following three options could be considered potential threats to impartiality in an audit context?

  • A. Experience
  • B. Competence
  • C. Intimidation
  • D. Self-audit
  • E. Familiarity

Answer: C,D,E

Explanation:
Potential threats to impartiality in an audit context include familiarity (having a close relationship with the auditee), intimidation (being coerced or feeling pressured), and self-audit (auditing one's own work). These factors can compromise the auditor's objectivity and the audit's integrity. References: = The information is based on the ISO 9001 Auditing Practices Group documents which discuss threats to auditor impartiality and how they may compromise an auditor's objectivity123.


NEW QUESTION # 107
What is the responsibility of the audit committee during an internal audit?

  • A. To define the audit schedule
  • B. To supervise all audit functions and activities
  • C. To establish an internal audit program

Answer: C

Explanation:
Comprehensive and Detailed In-Depth Explanation:
According to ISO 19011:2018, Clause 5.2 (Audit Program Management):
* The audit committee is responsible for establishing the internal audit program.
* The audit schedule (A) is determined within the program, but it is not the main role of the committee.
Thus, C is the correct answer.
Reference:
ISO 19011:2018, Clause 5.2 (Audit Program Management)


NEW QUESTION # 108
XYZ Corporation is an organisation that employs 100 people. As audit team leader, you are conducting a certification audit at Stage 1. When reviewing the quality management system (QMS) documentation, you find that quality objectives have been set for every employee in the organisation except top management.
The Quality Manager complains that this has created a lot of resistance to the QMS, and the Chief Executive is asking questions about how much it will cost. He asks for your opinion on whether this is the correct method of setting objectives.
Three months after Stage 1, you return to XYZ Corporation to conduct a Stage 2 certification audit as Audit Team Leader with one other auditor. You find that the Quality Manager has cancelled the previous quality objectives for all employees and replaced them with a single objective for himself. This states that "The Quality Manager will drive multiple improvements in the QMS in the next year". The Quality Manager indicates that this gives him the authority to issue instructions to department managers when quality improvement is needed. He says that this approach has the full backing of senior management. He shows you the latest Quality Improvement Request that was included in the last management review.

After further auditing, the issues below were found. Select three statements that apply to the term 'audit trail'

  • A. Decisions on improvement action timescales not involving departmental managers.
  • B. Evaluation of the results of the improvement action not always documented by the Quality Manager.
  • C. Top management claim not to be aware of the improvement request (QI/12/20/HR-3) initiated by the Quality Manager.
  • D. The single quality objective set for the organisation by the Quality Manager.
  • E. Limited knowledge of the content of Quality Improvement Requests by departmental staff.
  • F. Quality improvements not aligning with the quality policy.

Answer: A,B,E

Explanation:
Based on the scenario and the concept of an 'audit trail' within the context of ISO 9001, the three statements that apply would likely be:
A: Decisions on improvement action timescales not involving departmental managers. This indicates a lack of involvement and communication with those responsible for implementing the improvements, which is a key part of an effective audit trail1.
B: Evaluation of the results of the improvement action not always documented by the Quality Manager.
Proper documentation is essential for an audit trail, as it provides evidence that actions have been evaluated and are effective1.
C: Limited knowledge of the content of Quality Improvement Requests by departmental staff. An audit trail should ensure that all relevant parties are aware of and understand the actions being taken, which is not the case here1.
These points suggest issues with the communication, documentation, and involvement of relevant personnel in the quality management system processes, which are crucial for maintaining an effective audit trail and, by extension, a robust quality management system.


NEW QUESTION # 109
You are leading a Stage 2 certification audit of a multi-site organisation and have received the audit schedule below; Head Office and Site 1 - Day 1 Site 2 (150 Km from HQ) - Days 2 and 3 During Day 1 of the audit, the dient informs you that the laboratory at Site 2 has been dosed for decontamination due to a serious outbreak of an infectious disease among workers. In Site 2, all other functions could be audited as planned.
As the audit team leader, what would you do?
Choose the best acceptable action you could take:
Ask the audit Programme Manager for direction.
Complete the audit on day 3 and report back to the certification body for a certification decision.
Continue the audit on days 2 and 3 and return later to audit the Site 2 laboratory.
Immediately cancel the audit since the audit plan cannot be completed.
Who has the responsibility for assigning work to the audit team?

  • A. The audit team leader
  • B. The certification body
  • C. The auditee organisation
  • D. The audit team member

Answer: A

Explanation:
In the context of ISO 9001:2015 audits, it is the audit team leader who holds the responsibility for assigning work to the audit team. According to ISO 19011:2018 (Guidelines for auditing management systems, which complements ISO 9001:2015), the audit team leader is responsible for the organization and direction of the audit, including assigning specific roles and responsibilities to audit team members. This includes preparation of the audit plan, leading the audit, and ensuring that each team member understands their tasks.


NEW QUESTION # 110
You are conducting an audit at a single-site organisation seeking certification to ISO 9001 for the first time.
The organisation manufactures cosmetics for major retailers and the name of the retailer supplied appears on the product packaging. Sales turnover has increased significantly over the past five years.
You are interviewing the new Product Development Manager. You note that a software application called SWIFT is used to help control the product development process.
You have gathered audit evidence as outlined in the table. Match the ISO 9001 clause 8.3 extracts to the audit evidence.

Answer:

Explanation:

Explanation:
Audit Evidence and Applicable ISO 9001:2015 Clause 8.3 Extracts
* Half of all new products launched in the past 12 months were late. The Product Development Manager explains he has not got enough people on his team to cope with the demand for new products.# ISO 9001 Clause 8.3.2 e) - "...internal resource needs for the design and development of products and services..."
* The Product Development Manager explains many changes are made to cosmetic formulations during product development owing to retailer feedback. Only when confirmed by the retailer is the agreed formulation documented on SWIFT.# ISO 9001 Clause 8.3.5 - "...retain documented information on design and development changes..."
* The Product Development Manager explains that the customer confirms their approval to proceed with a new formulation by email. These emails are kept on SWIFT.# ISO 9001 Clause
8.3.6 - "...retain documented information on design and development outputs..."
* The Product Development Manager shows you evidence of consumer trials that are carried out for some new products before a full-scale launch.# ISO 9001 Clause 8.3.4 d) - "...conducted to ensure that the resulting products and services meet the requirements..."
* The Product Development Manager explains that an approved external laboratory is used to perform shelf-life stability trials on some formulations during product development.# ISO 9001 Clause 8.3.2 e) - "...external resource needs for the design and development of products and services..." ISO 9001:2015 Clause 8.3 (Design and development of products and services) requires organisations to plan, control, review, verify, validate, and document design and development activities to ensure products meet requirements.
Explanation of clause alignment:
* Clause 8.3.2 e) requires the organisation to determine both internal and external resource needs.
Lack of personnel causing late launches directly evidences internal resource shortfalls, while the use of an external laboratory demonstrates control of external resources.
* Clause 8.3.5 requires organisations to control design and development changes and retain documented information describing those changes, which is demonstrated by controlled updates in SWIFT following retailer confirmation.
* Clause 8.3.6 requires retention of documented information on design and development outputs, including customer approvals, which are evidenced by stored emails in SWIFT.
* Clause 8.3.4 d) requires design and development activities such as verification and validation, ensuring outputs meet requirements. Consumer trials prior to launch clearly meet this requirement.
ISO-aligned conclusion:
The evidence provided demonstrates structured control of product design and development, including planning, resourcing, change management, validation, and retention of documented information, all mapped directly to ISO 9001:2015 Clause 8.3 requirements.


NEW QUESTION # 111
What competence, among others, should each audit team member have?

  • A. Knowledge of the risk-based approach to auditing.
  • B. Knowledge of the industry in which the auditee operates.
  • C. A formal degree in quality management.
  • D. Expertise in each domain to be audited.

Answer: A

Explanation:
Comprehensive and Detailed In-Depth Explanation:
Auditors must have competence in risk-based auditing to effectively assess an organization's QMS performance and compliance.
Clause References:
* ISO 19011:2018, Clause 7.2.3 - Determining Auditor Competence:
* Auditors must have knowledge of risk-based thinking to assess risk impact on processes.
* ISO 9001:2015, Clause 0.3.3 - Risk-Based Thinking:
* The standard emphasizes proactive risk management, which auditors must understand.
Why is the Correct Answer B?
* Risk-based auditing ensures audits focus on high-risk areas, improving audit effectiveness.
* Auditors must assess how organizations apply risk-based thinking in decision-making, process control, and improvement.
Why are the Other Options Incorrect?
* A (Industry knowledge) # While helpful, it is not mandatory for all auditors.
* C (Expertise in all domains) # Auditors are not required to be experts in all areas, just in audit methodology.
* D (Formal degree in quality management) # ISO does not require a formal degree, just competence in audit principles and methods.
Reference:
ISO 19011:2018, Clause 7.2.3 - Determining Auditor Competence
ISO 9001:2015, Clause 0.3.3 - Risk-Based Thinking


NEW QUESTION # 112
Whistlekleen is a national dry cleaning and laundry company with 50 shops. You are conducting a surveillance audit of the Head Office and are sampling customer complaints. You find that 80% of complaints originate from five shops in the same region. Most of these complaints relate to damage to customer laundry.
The Quality Manager tells you that these are the oldest shops in the company. The cleaning equipment needs replacing but the company cannot afford it at the moment. You learn that the shop managers were told to dismiss most of the claims on the basis of the poor quality of the laundered materials.
On raising the matter with senior management, you are told that there are plans to replace the equipment in these shops over the next five years.
When reviewing the customer complaint file, you find that the organisation is facing a legal dispute with a customer over damage to an expensive cashmere coat.
Select the best option for how this should be handled by the Quality Management System.

  • A. Settle the court case by negotiation with the customer.
  • B. Report the situation to the customer with suggested remedial action.
  • C. Give an explanation to the customer of what went wrong.
  • D. Make an offer to replace the coat with a new one.

Answer: B

Explanation:
According to the ISO 9001:2015 standard, clause 10.2 requires organizations to review nonconformities, including any arising from customer complaints, and to take appropriate actions to determine the cause, implement corrections and preventive actions, and verify their effectiveness. The organization must also monitor the effectiveness of the actions taken and make changes if necessary.
In this scenario, the auditee is facing a legal dispute with a customer over damage to an expensive cashmere coat. This is a nonconformity that arises from customer complaint and has a significant impact on customer satisfaction and reputation. Therefore, clause 10.2 applies to this situation.
The best option for how this should be handled by the Quality Management System is B.
B means that the organization should report the situation to the customer with suggested remedial action. This option follows the principle of transparency and accountability, as well as respecting the customer's rights and expectations. The organization should also investigate the root cause of the damage and prevent it from happening again in other shops or products.
The other options are not appropriate because:
A means that the organization should settle the court case by negotiation with the customer. This option may not be feasible or satisfactory for both parties, especially if there is a large amount of compensation involved or if there are legal implications for other customers.
C means that the organization should make an offer to replace the coat with a new one. This option may not be sufficient or acceptable for both parties, especially if there is evidence of negligence or poor quality on behalf of the organization.
D means that the organization should give an explanation to the customer of what went wrong. This option may not be enough or convincing for both parties, especially if there is no evidence of negligence or poor quality on behalf of the organization.


NEW QUESTION # 113
......


PECB ISO-9001-Lead-Auditor Exam Syllabus Topics:

TopicDetails
Topic 1
  • Closing an ISO 9001 audit: The topic focuses on concluding a QMS audit and conducting audit follow-up activities.
Topic 2
  • Fundamental audit concepts and principles: Questions about interpreting and applying the main concepts and principles related to a QMS audit appear in this topic.
Topic 3
  • Conducting an ISO 9001 audit: It evaluates your skills to conduct a QMS audit.
Topic 4
  • Managing an ISO 9001 audit program: This topic evaluates your abilities to establish and managing a QMS audit program.
Topic 5
  • Preparing an ISO 9001 audit: This topic covers sub-topics related to preparing a quality management system audit.
Topic 6
  • Fundamental principles and concepts of a quality management system: The main objective of this domain is to evaluate your skills of explaining and applying ISO 9001 principles and concepts.

 

ISO-9001-Lead-Auditor Free Certification Exam Material with 250 Q&As : https://www.ipassleader.com/PECB/ISO-9001-Lead-Auditor-practice-exam-dumps.html

New Version ISO-9001-Lead-Auditor Certificate & Helpful Exam Dumps is Online: https://drive.google.com/open?id=1NS8O2AaqzXEdCvUiEcCr6LAt8D649ejg